Kungsåra, Sweden´s currently largest PV park soon to be completed

Our first PV park, Kungsåra, about 1,5 miles from Västerås, will soon be finished. Commissioning is planned for the summer of 2023. Construction of the park began in 202209, so in just about 10 months we will be able to deliver scarce 22 MW of renewable energy to Sweden´s power grid from the time we put the shovel in the ground. It corresponds to 11 million driven miles with an electric car, which translates to the annual consumption of roughly 7300 electric cars. During the spring the park will be sown with flowering species to benefit the local biodiversity